An activity has a optimistic duration estimate of 2 days, a mostly likely estimate of 5 days, and a pessimistic estimate of 8 days. What is the weighted average duration? A. 4 B. 5 C. 5.2 D. 5.5 E. 6 |
哪些内容不适合这里 · · · · · ·
请尊重创作者的劳动,不要在讨论区里提供或讨论下载方面的内容。

2008-05-20 01:16:39 奔跑的蜗牛
B(O+4M+P)/6 = 5
竟然有5个选项,这是老版的题目了,别浪费时间在这上面了